  • Crews have completed 100% of the rigid inclusions at the new Macon Arena, City of Macon-Bibb said.1
  • As of Monday, compaction in the north parking lot has reached 95%.1
  • Work on aggregate piers is nearly complete, with crews finishing the remaining work near the future ice rink.1

Crews are making progress on the groundwork needed to bring the future entertainment destination to life, with several major construction milestones already completed, City of Macon-Bibb said.1

Crews have completed 100% of the rigid inclusions, a vital step in strengthening the ground that will support the new facility, City of Macon-Bibb said.1

Work on aggregate piers, which also help stabilize the soil beneath the building, is nearly complete, with crews finishing the remaining work near the future ice rink, City of Macon-Bibb said.1

Soil Compaction and Asphalt Removal

Crews have been busy moving and compacting soil throughout the property, City of Macon-Bibb said.1

A large mound of soil has been reduced to about half its original height, City of Macon-Bibb said.1

As of Monday, compaction in the north parking lot has reached 95%, and asphalt removal across the property is complete, City of Macon-Bibb said.1

Soil compaction helps prevent future settling and cracking in parking lots, concrete slabs, and foundations, City of Macon-Bibb said.1

While much of this work is happening underground, it’s an important part of making sure the new Arena is built on a strong foundation, City of Macon-Bibb said.1

Utilities and Progress

Crews are making progress on utilities, including protecting manholes and beginning sanitary sewer excavation on the north side of the property, City of Macon-Bibb said.1

“It’s exciting to see how much progress is being made, even if people driving by can’t see all of it just yet,” said Mayor Lester Miller.1 “This is a major investment in Macon’s future, and we’re making sure it’s done right from the ground up. When those doors open, I want people to be proud of what we’ve built together.”1

Arena Features and Timeline

The Macon Coliseum was where people from Macon, Middle Georgia, and the entire state created memories for nearly 60 years, City of Macon-Bibb said.1

The new Macon Arena is slated to open in late 2028, City of Macon-Bibb said.1

The Arena includes a seating bowl that has the flexibility to reconfigure for different concert arrangements, sporting events, competitions, family entertainment, community programming, conventions, and other entertainment events, City of Macon-Bibb said.1

Premium seating — comprised of luxury suites, club suites, and loge boxes — will be provided in addition to the bowl capacity, City of Macon-Bibb said.1

Capacity will vary based on the event being hosted, with max capacity being realized with a center stage concert and using the flex hall for 12,298 people, City of Macon-Bibb said.1

An approximately 35,000-square-foot flex hall will be attached to provide ancillary program space, including capacity for an additional ice sheet, tradeshows, conferences, and various high school sporting events, City of Macon-Bibb said.1

The flowing lines of the exterior are meant to replicate the flow of the Ocmulgee River, and the alignment of the facility is a direct line to the Ocmulgee Mounds National Historical Park, City of Macon-Bibb said.1

There will be dedicated space inside the building for the Macon Sports Hall of Fame, City of Macon-Bibb said.1

A study was conducted to help ensure maximum visibility from every seat for any type of event being held, City of Macon-Bibb said.1

Report an error in this story

Sources

The numbers in the story point here. Each one links to the original article.

    See a sentence its source doesn’t back up?

    Tell us the source number and what’s wrong. We check every report. If we change the story, the fix goes on the corrections page with the old wording.